Friday, May 20, 2022

40 NEW PMI-CAPM Free Questions and Answers (Part - 2)

 

This is in continuation of the earlier series of questions for the PMI-CAPM® examination. 

I would definitely suggest that you take both the parts together when you try to attempt the questions. 

Again, do note that these are not verbatim questions from the PMI-CAPM exam, however, these questions cover the areas needed for the exam. The questions are based on the PMBOK Guide, Exam Content Outline and Agile practices associated with the PMBOK guide.

As noted in the earlier post, to answer these questions, you need to have:

  • Good grasp on Knowledge Areas of the PMBOK Guide, 6th edition. 
  • Good grasp of the introductory areas of the PMBOK guide such as Project Life Cycles, Project Environment and Role of Project Manager. 
  • Sound understaning of the Agile practices as per the PMBOK guide.
  • Understanding the content of the ECO. The ECO is a small, barebone document listing the possible (not all) topics/areas to be covered for the CAPM exam.

These questions are referenced from CAPM Live Lessons - Guaranteed PassCAPM 23 Contact Hours and the book, I Want To Be A CAPM.

I hope you enjoy doing these questions and it helps in your preparation for the PMI-CAPM exam.

[This series - Part - 1]

*********

Question – 21: Risk management is crucial for project success. However, a common problem in risk management is – 

A Project teams spend less effort in identifying and analyzing risks
B No proper approach in developing risk responses
C The risk register and risk report are not frequently updated
D No action is taken to manage the risk

Question - 22: All of the following statements about work breakdown structures are true EXCEPT:

A They provide a basis for estimating the project.
B They prevent work from slipping through the cracks.
C They help to organize the work.
D They are created by the project manager.

Question - 23: In which part of the risk management process would you complete a risk rating matrix?

A Plan Risk Responses
B Identify Risks
C Perform Qualitative Risk Analysis
D Implement Risk Responses

Question – 24: For agile life cycles risks are managed and controlled:

A As requirements change
B As requirements and constraints emerge
C By detailed planning
D By progressive elaboration of initial plan

Question - 25. During initial stakeholder identification, which project document will act as an input?

A Issue Log
B Change Log
C Requirements Documentation
D No document is used

Question - 26: The Scope Management processes are generally completed in which order?

A Collect Requirements, Define Scope, Create WBS, Control Scope
B Collect Requirements, Define Scope, Create WBS, Validate Scope
C Define Scope, Validate Scope, Collect Requirements, Create WBS
D Validate Scope, Collect Requirements, Define Scope, Create WBS

Question – 27: Which one of the following is correct for the project deliverables in Adaptive Life Cycle?

A Defined at the beginning of the project and managed throughout
B Developed over multiple iterations and approved at the beginning of each iteration 
C Defined at the beginning of the iteration and approved for each iteration
D Defined at the beginning of the release and then developed and re-adjusted throughout

Question – 28: Closing process group has processes to formally complete all of the following ones, EXCEPT _________________:

A Project
B Phase
C Contract
D Phase gate

Question - 29: You must start a building project tomorrow to meet the deadline. What type of contract should you sign to start the building work?

A Time and material (T&M)
B Cost plus fixed fee (CPFF)
C Fixed-price (FP)
D Fixed price economic price adjustment (FP-EPA)

Question - 30: All the following are part of a communications management plan EXCEPT:

A Names of the stakeholders who can talk to the project manager.
B Names of the stakeholders and instructions on sending project status to them.
C Names of those receiving a telephone call when the system crashes.
D Methods used to collect and store information.

Question – 31: Who is not within the immediate sphere of influence of the project manager?

A Sponsor.
B PPP managers.
C Project Team.
D Resource Managers.

Question - 32: Which of the following is TRUE of inspections?

A They test the future desires of prospective customers.
B They can only be conducted on the final product.
C They are not to be conducted by the project team.
D They prevent defective deliverables from reaching the customer.

Question – 33: Tailoring project management to the project is necessary MAINLY because:

A Every project is unique 
B Project creates a product or service or result
C Project is a temporary endeavor
D Project enables business value creation


Question - 34. A daily stand-up for an Agile project can happen in: 

A Monitor Stakeholder Engagement
B Plan Stakeholder Engagement
C Identify Stakeholders
D Manage Stakeholder Engagement


Question - 35: What is the focus of the Manage Quality process?

A Determining how quality will be defined and validated
B Analyzing the effectiveness of project processes
C Comparing the project metrics against the project management plan
D Confirming and documenting the achievement of agreed-to requirements


Question - 36: You want to let your team know the weekly project status report is now officially due by 4:00 pm on Thursdays. Which type of communication would you use?

A Informal written communication
B Formal verbal communication
C Formal written communication
D Informal verbal communication

Question – 37: Which one of the following minimizes scope creep?

A Release length.
B Level of accuracy.
C Control thresholds.
D Timeboxing.

Question – 38: An activity in a network has the following characteristics: ES = 12, EF = 22, and LS = 14. The duration of the activity is:

A 8 weeks
B 11 weeks 
C 12 weeks
D 14 weeks

Question – 39: WBS contains all the following work, EXCEPT:

A Project work
B Product work
C Project management work
D Product management work

Question - 40: In which parts of the cost management process is earned value (EV) used?

A Reserve analysis 
B Creating the cost baseline 
C Variance management planning
D Forecasting 

*********

The question set is available in the embedded document below. The answers are also part of this document.

For all answers, subscribe to this site and send a mail (from your GMail id) to managementyogi@gmail.com. You can subscribe by using the Subscribe widget on the top-right corner of this site.



CAPM Live Lessons - Guaranteed Pass:

CAPM 23 Contact Hours Course:

Thursday, May 19, 2022

40 NEW PMI-CAPM Free Questions and Answers (Part - 1)

 

The Certified Associate in Project Management (CAPM®) exam from PMI is solely based on the PMBOK® Guide, 6th edition. The exam blueprint, however, is based on the Exam Content Outline (ECO) for the CAPM exam. The PMBOK guide covers a vast area in project management and includes a good number of Agile concepts and practices. In this post series we will have 40 PMI-CAPM questions.

These questions are referenced from CAPM Live Lessons - Guaranteed PassCAPM 23 Contact Hours and the book, I Want To Be A CAPM. Do note that these questions are not directly from the CAPM exam, but based on my understanding and feedback from successful CAPMs.

To answer these questions, you need to have:

  • Good grasp on Knowledge Areas of the PMBOK Guide, 6th edition. 
  • Good grasp of the introductory areas of the PMBOK guide such as Project Life Cycles, Project Environment and Role of Project Manager. 
  • Sound understaning of the Agile practices as per the PMBOK guide.
  • Understanding the content of the ECO. The ECO is a small, barebone document listing the possible (not all) topics to be covered for the CAPM exam.

This is the first of the series with 20 questions. The next part has another set of 20 questions.

I hope you enjoy doing these questions and it helps in your preparation for the PMI-CAPM exam.

[This series - Part - 2]

*********

Question – 1: Networking, used as a tool and technique in Manage Communications process, can do all of the followings, EXCEPT: 

A Gives access to information organization
B Influences stakeholders' actions
C Increases stakeholders' support
D Removes barriers to communication


Question – 2: As you implement the agreed upon risk responses created for the risks, all of these can be done, OTHER THAN: 

A Address overall project risk exposure
B Maximize individual opportunities
C Minimize individual threats
D Evaluate the effectiveness of risk responses.

Question – 3: You resolved a conflict between two members, but again they got into fighting. What conflict resolution approach should help you BEST?

A Collaborate
B Smooth
C Compromise
D Direct

Question – 4: For stakeholders with high power, but low interest, you should: 

A Keep them satisfied.
B Manage them closely. 
C Monitor them continuously. 
D Keep them informed.

Question – 5: For successful communication, you need to FIRST:

A Develop a communication strategy.
B Find out the various communication dimensions to use in the project.
C Determine the activities and artifacts of communications.  
D Develop a communication management plan. 

Question – 6: You are giving certificates of appreciation and also corporate apparel with a team logo to your team members. These can be taken from:

A Enterprise Environmental Factors 
B Organizational Process Assets 
C Project management information system 
D Is to be purchased from the outside

Question – 7: The procurement decisions are decided and documented in _______________ process.

A Plan Procurement Management 
B Conduct Procurements 
C Control Procurements 
D Plan Project Management

Question – 8: You want to find out the reasons for accidents on a construction project. Which one of the following would be BEST to use?

A Check sheet.
B Why-why diagram.
C Pareto diagram.
D Scatter diagram. 

Question – 9: A ceiling price is MOST LIKELY to be set in which contract?

A Fixed price incentive fee (FPIF) 
B Fixed price with economic price adjustments (FPEPA) 
C Cost plus fixed fee (CPFF) 
D Time and material (T&M)

Question – 10: A self-organizing team functions with an absence of centralized control. Such teams are BEST supported by:

A Generalizing specialists. 
B Critical resources at the right time. 
C Adaptive team members. 
D Emotionally intelligent team members.

Question – 11: In an agile environment, communications artifacts are put in a transparent manner. These are known as: 

A Checkpoints 
B Artifacts 
C Information Radiators 
D Information Reports

Question – 12: The period of time that may elapse after a risk has occurred before a risk's impact is discovered, is known as:

A Risk Urgency
B Risk Proximity
C Risk Detectability
D Risk Dormancy

Question – 13: Stakeholder Engagement Assessment Matrix is used in which process(es) of Communications Management KA? 

A Plan Communications Management
B Manage Communication
C Monitor Communications
D Both Plan Communications Management or Monitor Communications


Question – 14: All of the followings are part of Risk Report, EXCEPT:

A Assessment of overall project risk exposure. 
B Detailed probabilistic analysis of the project.
C Prioritized list of overall project risks. 
D Recommended risk responses.

Question – 15: You want to evaluate if the quality objectives have been achieved. For this purpose, you should use:

A Checklists
B Requirement Traceability Matrix
C Test and Evaluation documents
D Inspection

Question – 16: Actual assignment of resources - team and/or physical - happens in which process group?

A Initiating
B Planning
C Executing
D Monitoring and Controlling

Question – 17: Control Quality process is about ___________________ deliverables, whereas Validate Scope is about ________________ of deliverables.

A Verification, Implementation
B Testing, Inspection
C Completeness, Correctness
D Correctness, Acceptance

Question – 18: The responsibility for the Organizational System lies with the:

A Project Manager
B Organizational Management
C Organization's PMO
D Stakeholders, including Senior Management

Question – 19: To find out the seller processes, procedures, or products that are out of compliance, you can use:

A Quality reports 
B Risk Report
C Audit Report
D Performance Report

Question – 20: At the end of the day, leadership and management are ULTIMATELY about:

A Ability to get things done 
B Ability to deal with politics
C Understanding when to be flexible with tactical priorities
D Selecting the right kind of power to influence and negotiate with others 

*********

The question set is available in the embedded document below. The answers are also part of this document.

For all answers, subscribe to this site and send a mail (from your GMail id) to managementyogi@gmail.comYou can subscribe by using the Subscribe widget on the top-right corner of this site.