Tuesday, June 04, 2019

30 NEW PMI-ACP Free Questions and Answers (Part - 2)




This is in continuation of the earlier series of questions for PMI-ACP examination. 

[This series - Part - 1] 

I would suggest that you take this one and earlier post of 30 PMI-ACP Freee Questions Part - 1 together, when you do your practice. Note that these are not verbatim  questions from PMI-ACP exam, however, these questions covers the domains, references books and guide for the exam. 



The questions are from the newly released book:
I Want To Be An ACP, 2nd edition. 


[This series - Part - 1]



*********

PMI-ACP QUESTIONS (Part – 2)


Question – 16: For a customer service project which will be using robots, your team has been formed with a set of specialists as well as generalists. The team members are striving to be generalizing specialists. However, your team is a small one with rapid changes, you want to have your team members deeper experiences across various disciplines. What should you do?
A Team member should be encouraged to have broken-comb skills.
B Team members should be more self-aware, self-organized, self-managed, and cross functional.
C Team should have more intraspectives as well as retrospectives.
D Follow practices such as pair programming, whole team and sit together.



Question – 17: A release burndown chart for a project is shown in the below figure.



Based on it, can you as the Scrum Master can interpret which one of the following?
A On an average 30 story points are added in every Sprint and also completed.
B On the 4th Sprint, the total work in story points is 180.
C While 30 story points were completed in 5th Sprint, 20 story points were also added.
D Being 4th and 5th Sprints, there has been no change in scope.  


Question – 18: For an infrastructure project, your designers are not sure of the architecture. Some of your key stakeholders proposed to have a thin slice of the system, which can be used to determine the potential architecture of the system. The slice to cover all the possible layers of application to validate the potential architecture. This slice will be a prototype and will not be used in production, but only for demonstration. What should you do?
A Create a user story for the potential architecture.
B Develop an architectural spike to determine the potential architecture.
C Build analysis stories which will help to find other stories.
D Create a set of infrastructure stories. 


Question – 19: You are facilitating a planning poker estimation meeting, where your team is following the steps such as reading the story, providing an estimate and discussing the differences. For one backlog item, one team member informed that this story is pretty much nothing and very little work is needed. This is much lower than the features estimated to be 1 story point.  What should you do NEXT?
A Switch to T-shirt size estimation approach.
B Assign a value of 0 or 1/2 for this story.
C Mark "?" for this story and remove it from the backlog.
D Mark "∞" for this story and continue working on other items.


Question – 20: A product backlog has 400 story points worth of work and total budget estimated is $200,000. At the end of fourth iteration, actual cost is 42,500 and total story points completed so far is 90. If the baseline velocity is 25 story points, what can be set about this project?
A Project is ahead of schedule, but over budget.
B Project is behind schedule, but under budget.
C Cost performance of the project is bad.
D Schedule performance of the project is good.


Question – 21: A user story is written as "As a <team member>, I want to know what the key stakeholders expect from the payment part of this system, so that I can find stories to work on." The story is not timeboxed yet and brought in for discussion in a backlog refinement meeting. However, as your team members are not sure what kind of story it is and how to proceed, you should FIRST inform, it's a:
A Spike story.
B Infrastructure story.
C Analysis story.
D Architecturally significant story.


Question – 22: Your team is developing a social media product. Some of your engineers, including UX engineers, are part of other teams and work in your project as and when needed because of organizational constraints. Your product work progressed well and many items have been successfully reviewed in earlier two sprint review meetings. However, the stakeholders are not satisfied with the way the user experience has been addressed. What should you do FIRST?
A Have refined requirements for UX related items.
B Ensure all engineers are 100% dedicated to your team.
C Make the UX engineer part of your team. 
D Have a clear definition of ready for the UX items 


Question – 23: A team has been working on a process improvement project with flow-based approach and using Scrumban method for its work. Whenever an impediment is identified and it looks to be blocking in nature, the team uses swarming to collectively work and focus on the impediment till it is resolved. Which one of the following BEST describes roles in team swarm?
A Coordinators, Swarmers and TeamLets.
B Team Members, Flow Master and Process Owner.
C Swarmers, Mobbers and Coordinators.
D Manager, Doomsayer, and Tracker. 


Question – 24: For a system development project, your team is following Scrum Practices. For the current Sprint, your team has committed a number of items from the product backlog. Mid-way into the Sprint, the team strongly felt that they won’t be able to complete many items. As you checked and discussed with the team along with the Product Owner, you found that if those items can't be delivered, then the Sprint Goal will be jeopardy and the Sprint will lose its value. What should you do NEXT as the Scrum Master?
A Cancel the Sprint.
B Abnormally terminate the Sprint.
C Ask the team members to deliver the items which they can.
D Let the team self-organize and find a way to resolve.


Question – 25: You are working as a project manager to develop the portal of a banking organization. There are many requirements and technological uncertainties, which necessitates risk management. You have defined the risk probabilities and impact for this project before the first iteration planning meeting. Your team members are now identifying the risks. However, you want to have better visualization. What should you do?
A Create a risk probability and impact matrix and share with your team.
B Prepare a risk register and ask the team to add new risks to this register.
C Have a risk map prepared, add color coded sticky notes representing the risks with severities.
D Find out the risk scores and prepare a risk burndown chart. 


Question – 26: You project has completed two releases and currently you are in the 7th iteration. There have been many risks identified throughout and now you want to check the effectiveness of risk responses in dealing with these risks and want to have a risk audit. Which one of the following is the BEST place to conduct such activities?
A Retrospectives.
B Iteration planning meeting.
C Daily stand-up meeting.
D Product Demo.


Question – 27: A drug company is working on a new drug product where requirements are not fully known, the technology platform is changing and also has high uncertainties. The organization hence decided to use an agile mode of development for this product. However, for the final drug approval, the Government agencies demand work to be stable, a product to be known because the regular has a clear process to work through on it. Which one of the following hybrid models will be MOST appropriate?
A Predominantly Predictive with Agile model.
B Predominantly Agile with Predictive model.
C Combined Agile and Predictive model.
D Agile-Predictive hybrid model.


Question – 28: Reviews in agile approaches are not only limited to product work, but can be used for other ones such as continuous improvement. Which one of the following is not a type of review?
A Product demo
B Technical review
C Risk status review
D Team performance evaluation 


Question – 29: A media publishing house team has been using Scrum for its journal publications. The agile coach for the team continuously reminds the team to join the daily stand-up, update the burndown chart, complete the tasks and update them on the task board, among others. Which coach mode is displayed by this coach?
A The Nag
B The Heckler
C The Admin
D The Megaphone 


Question – 30: Your release is coming to an end which has 5 iterations. Currently, for the release retrospective, your team members are writing significant events during the release on index cards and putting them on a timeline in a chronological order. Team members are then using color coded stick dots for feelings about those events, i.e., blue for sad, yellow for mad, orange for surprise and green for glad. Which activity (or activities) the team is performing?
A Team Radar
B Timeline with Triple Nickels
C Timeline with Color Code Dots and Mad Sad Glad
D Timeline with Color Code Dots


[This series - Part - 1]

The question set is available in the embedded document below. The answers are also part of this document.

For all answers with detail explanation, subscribe to this site and send a mail (from your GMail id) to managementyogi@gmail.com.



Monday, May 20, 2019

30 NEW PMI-ACP Free Questions and Answers (Part - 1)




These questions are based on feedback from many successful PMI-ACPs and my understanding of various Agile concepts. Some of the questions references the latest list of guide/books for the exam. 


The questions are from the newly released book:
I Want To Be An ACP, 2nd edition.

Questions in the PMI-ACP exam are mostly situational. You should have sound understanding of agile principles, values, practices as well as real-world experience to try out the questions. 

In this series, there are 15 questions, which you can try. I believe it will help you in your PMI-ACP exam preparation.

[This series - Part - 2]



*********

PMI-ACP QUESTIONS (Part – 1)


Question – 1: You are working in a large industrial project to develop intelligent military devices. There are multiple Scrum teams working together. Your team is running daily meetings for every sprint. However, there is also a need for representatives from each Scrum team to meet 2 to 3 times a week and synchronize the work for the Sprints completed. What team method or scaling method is MOST suitable for your project?
A Lean and Kanban.
B Scrum of Scrums.
C Large Scale Scrum.
D Extreme Programming.


Question – 2: You are working in a software development project which follows the follow-the-sun model, where work is handed off at the end of every day from one development site to another due time zone gaps. The entire team is following the Scrumban method. Team members of one site had asked to have the burn down chart and velocity histogram is to be available to all. What should you do?
A Inform the team that it's not possible as the team members are geographically separated.
B Bring up the chart and histogram in the next retrospective meeting.
C Put an electronic information radiator with these charts within the fishbowl window.
D Assign a person to generate the chart and histogram and share with the site members.


Question – 3: An agile practitioner is leading a critical project to build a deep learning neural system. Several prototypes have been developed by the team, but the top management is not satisfied with the results. In one meeting, the leader lost his cool and yelled at the team members for building useless prototypes, which are unable to satisfy management. Which one of the agile principles did the leader forget?
A Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage. 
B Agile processes promote sustainable development. The sponsors, developers, and users should be able to maintain a constant pace indefinitely.
C Build projects around motivated individuals. Give them the environment and support they need, and trust them to get the job done.
D At regular intervals, the team reflects on how to become more effective, then tunes and adjusts its behavior accordingly.


Question – 4: Large scale scrum (or LeSS) is a scaling approach which uses Scrum, but with a large number of teams at a larger scale. Which one of the following LeSS practices are similar to the team based method of Scrum?
A Overall retrospective.
B Cross-team coordination.
C Cross-functional team.
D Overall Sprint Review.


Question – 5: You are negotiating for a contract with a prospective client. In the project high requirements churn is expected. Your organization has the domain expertise, but you are worried about the scope change and the client is also telling the price is fixed. However, the client agrees that if any higher priority feature is to be added in a future iteration, then the lower priority item has to be removed from the release plan. What should you do?
A Don't pursue this contract as scope is changeable, but price is fixed.
B Ask for a premature clause for the contract closure, i.e., an early cancellation approach
C Propose a fixed price with allowed scope change contract
D Go for team augmentation approach with the client 


Question – 6: In a product backlog, there are 4 features shown below with cost of delay and duration. How should the product owner prioritize these features?

A Feature D will be of the highest priority.
B Feature C will be of the lowest priority.
C Both Feature A and Feature B will be of the same priority.
D Feature B will be of the highest priority followed by Feature D. 


Question – 7: Your team is working on an e-ticket reservation for booking flights and following a Kanban approach to development. The team has a board which has been divided into various workflow states such as Backlog, Selected, Develop, Deploy, and Live. What is the PRIMARY purpose of this board?
A To find the defects in the system and throughput.
B To self-organize and find out the bottlenecks in their workflow states.
C To create an expedite lane for high priority customer features.
D To visualize how features flow through a process and determine right work in progress limit. 


Question – 8: A product owner (PO) is prioritizing a list of capabilities, features, and stories considering various factors. While doing so, the PO notices that two items in the backlog can be completely eliminated altogether because these operation tasks are not needed. What factors did the PO consider for prioritization?
A Financial Value.
B Value and Risk.
C Cost of development.
D Knowledge gained. 


Question – 9: Your organization is building an Agile PMO as a center of excellence and helping the agile practitioners engaged in various projects. Which one of the following cannot be a service provided by the Agile PMO?
A Facilitate organizational learning.
B Create and maintain the product backlog of the teams.
C Ensure that teams’ work fits into the overall organizational strategic vision.
D Inform on compliance and amplify the teams’ external needs regarding compliance. 


Question – 10: You are working as an agile practitioner for a network hosting services project. A new stakeholder in a release planning meeting is unsure about this project and wants to know who benefits from this project and how they benefit. What should you do?
A Share the benefits management plan with the stakeholder.
B Request the stakeholders to participate in the iteration planning meeting.
C Send the project charter of the project to the stakeholder.
D Use the team charter to explain the benefit details. 


Question – 11: Your team is working on a smartphone project and has created a number of user stories which will be implemented over multiple iterations. Your sponsor wants to ensure that all possible scenarios addressed and have stories you would be likely to miss otherwise. He gives an example of how smartphones are used in very cold climates. What should you do NEXT?
A Use the 20:20 vision collaboration games.
B Specify requirements in form of executable customer tests.
C Consider using low fidelity prototypes. 
D Build extreme characters to get such types of users.


Question – 12: Your team is rebuilding an existing product for a client organization. Your client does not remember all the usages, pitfalls or lacunae in the product and hence asked you to actively participate with them while using the product. These will uncover the hidden requirements and hence build a better version of the product. Which innovation game will be MOST effective for this purpose?
A Me and My Shadow.
B Start Your Day.
C The Apprentice.
D Remember the Future.


Question – 13: A project team has been building a mobile commerce application product. The earlier version of the product didn't work in the market because of one particular reason - lack of customer empathy. The client organization informed the earlier product built by individuals with good domain knowledge, but no real on-the-field experiences of users working on the product. If you were the leader of the project, what would you do?
A Build an exhaustive product backlog with fine-grained requirements.
B Involve users in the iteration planning meeting.
C Use the innovation game of "The Apprentice" to have customer empathy.
D Ensure active stakeholder participation.


Question – 14: Your team is following Scrum framework for product development. Currently, you are documenting the roles and responsibilities for all the roles of your team including development team members, product owner and scrum master. You are using RASCI matrix for this purpose. Which one of the following roles will fall under "S" category?
A Development team members.
B Product Owner (PO).
C Scrum Master (SM). 
D Business owner and external stakeholders. 


Question – 15: You are the project manager for a mono-rail project in an organization, which has been following XP practices. Your sponsor wants to spread knowledge gained during the execution of the project and thinks knowingly keeps one member at a reduced load, but keeping the overall team load will help in knowledge spread. This way you can also free-up a team member. Which XP practice will help you the MOST in this aspect?
A Slack.
B Team continuity.
C Pair programming. 
D Shrinking team.


The question set is available in the embedded document below. 

For all answers with detailed explanation, subscribe to this site and send a mail (from your GMail id) to managementyogi@gmail.com.


Wednesday, June 18, 2014

30 Free Questions with Answers on PMI-ACP Examination (Part - 2)




The questions for PMI-ACP have changed. For the latest questions, refer the below link.
 
[NEW PMI-ACP Questions and Answers on Latest PMI-ACP Exam (Link)]
 
It has been quite sometime since I have had my blog post. I could not write in last few months. Nevertheless, I check your mails and respond whenever I can. [This series - Part - 1] 

This one - the free question set on PMI-ACP - has been long pending. A number of people have asked on it. I keep on getting mails on it. Some people have mentioned it is very close to the real exam. And there are comments on this blog as well.  


Would suggest that you take this one and earlier post of 30 PMI-ACP Freee Questions Part - 1  together, when you do your practice. Note that these are not verbatim  questions from PMI-ACP exam, however, the essence of the exam is there. 

Question – 16: Below are the number of stories to be developed in a team. In first iteration, the team was able to complete Story A, Story B, and 50% of Story C. What is the velocity of the team?

A)   9
B)   11
C)   5
D)   4

Note: I remember some additional questions being asked on the same table and there are graphical questions based on burndown chart. You need to be clear in your understanding on those aspects.

Question – 17: Earned value management is Agile project is most appropriately used at which level?

    A)   Story

    B)   Task
    C)   Iteration
    D)   Release

Question – 18: As per Lean methodology in Agile framework, which one of the following is true?


    A)  Most errors are due to oversight of the resources and skill gaps
    B)  Most errors are systematic in nature
    C)  Most errors are due to motivational issues in the team
    D)  Most errors are due to management oversight and organisational structure 

. . . 

. . .



The question set is available in the embedded PDF below. 

For all the questions and answers, subscribe to this blog (on top right corner of this blog) and send a mail, from your gmail id to managementyogi@gmail.com







You may also like:


Wednesday, June 19, 2013

30 Free Questions with Answers on PMI-ACP Examination (Part - 1)


The questions for PMI-ACP have changed. For the latest questions, refer the below link.

  [NEW PMI-ACP Questions and Answers on Latest PMI-ACP Exam (Link)]



[ This series - Part - 2 ]

The questions are based on my personal experience in the PMI-ACP examination. Though I tried a few questions from a few providers, did not find any one closer to the real PMI examination. The questions in the exam are rarely direct and always tests your understanding. 

In this series, there are 15 questions (close to the real examination). 



Question – 1: Velocity is used for Iteration as well as Release Planning. It is typically the sum of delivered user stories. Which of the following is not TRUE about velocity?

A)    Even if the work is fully complete other than few bugs, it will not counts towards velocity
B)    While measuring with velocity, there is no scope to correct estimation errors
C)    As velocity informs on all the "done" stories, in a way it tracks the customer satisfaction
D)    Velocity does not inform on the productivity of the team


Question – 2: Which one of the following is correct about Kanban?

A)    No estimation is required in Kanban
B)    In Kanban Team Leader plays the Role of Coach as in XP
C)    Team focuses on completing features as quickly as possible but is not constrained by a time-box
D)    All of the above
  
Question – 3: An user story is very useful for the project. Till what time, the user story cards are considered relevant in an Agile project?

A)    End of iteration
B)    End of release
C)    End of project
D)    When work related to the story is complete
. . .
. . .

The question set is available in the embedded PDF below. 