By Manas Das, PMP
Critical Path Method (CPM) is known as one of the key schedule network analysis techniques in “Develop Schedule” process of Time Management knowledge area, under planning process group.
This analysis is applied on the schedule network diagram, which is created in “Sequence Activities” process – also in Time Management knowledge area and planning process group.
The simplified diagram with the only the key input and outputs, along with the CPM technique is shown below.
What is Critical Path?
Let’s see the definition of critical path.
“Critical path is the shortest possible duration within which the project will be completed or critical path is the longest path in the network.”
Above two lines defining critical path may look contradictory to you, but they are not! It means if the critical path is delayed, then the project’s end date will be pushed. Hence it is the shortest possible duration within which the project will be completed. The other aspect – longest possible path, informs us that if you delay on this path, of course the project duration will be elongated.
It’s worth to understand that activities on a critical path are critical from schedule point of view only and not from functionality or complexity point of view. Project management practitioners, who are new to this concept, confuse on this. All activities on the critical path are known as critical activities.
Again, the activities are critical, because if you delay any activity on critical path, the project end date will be pushed further.
More the number of critical paths, more the risks to the project. Let’s check this scenario. Imagine you have a schedule network diagram with multiple critical paths. As it has many critical paths, you can say that there are multiple ways in which the schedule can be delayed. Hence, more risks.
Let’s take an example to understand more on it. Below, a simple network diagram is shown with various activities. The duration of the activities is in days, e.g., Activity A is of 5 days duration.
There are 3 different ways to complete the tasks which will take different time to complete as below.
Path -1: Start – A - B – D – F – End = 16 days
Path-2: Start – A – B – E – F – End = 15 days
Path-3: Start – A – C – E – F - End =11 days
But Critical path is Start – A – B – D – F - End being the longest path which takes 16 days to be completed.
Second Definition of Critical Path
There is another definition of critical path as well, which you can see while using project-portfolio management tools such as Microsoft Project or Oracle Primavera. It goes as follows.
“Critical path is the network path in which the total float of activities can be less than or equal to zero.”
Total Float and Free Float
To understand the second definition of critical path, first it requires to understand what total float and free float.
There are two types of floats.
For critical tasks, Total Float can be “0” or can be “Negative”. Critical tasks will have Free Float as “0”. To understand it with an example, you can refer this post:
Primavera P6 - Critical Path is Not Always The Longest Path
Taking one of the figures from the above article, we have two critical paths shown, which are highlighted in read in the graphical side of the Schedule Layout.
Critical Path 1: Start – Activity A – Activity B = 5 days
Critical Path 2: Start – Activity E – Activity – Finish = 8 days
As you can see Activity A is not on the longest path (the path is only of 5 days duration), but still it is highlighted as a critical activity. Because this activity has negative total float of value “-1 day”. Of course, the other two activities – Activity E and F are critical activities, because their TF values are zeroes.
References:
1. “6.6.2.2: Critical Path Method” from PMBOK Guide 5th Edition.
2. “6.7.2 Critical Path Method (CPM)” from Book - I Want To Be A PMP by Satya Narayan Dash.
Brief Profile: Manas Das, Project Manager Infosys Technologies
Manas Das has 12+ years of work experience and is playing a Project Manager role for retail portfolios in NA geography for Enterprise Application Services.
You may also like:
Critical Path Method (CPM) is known as one of the key schedule network analysis techniques in “Develop Schedule” process of Time Management knowledge area, under planning process group.
This analysis is applied on the schedule network diagram, which is created in “Sequence Activities” process – also in Time Management knowledge area and planning process group.
The simplified diagram with the only the key input and outputs, along with the CPM technique is shown below.
What is Critical Path?
Let’s see the definition of critical path.
“Critical path is the shortest possible duration within which the project will be completed or critical path is the longest path in the network.”
Above two lines defining critical path may look contradictory to you, but they are not! It means if the critical path is delayed, then the project’s end date will be pushed. Hence it is the shortest possible duration within which the project will be completed. The other aspect – longest possible path, informs us that if you delay on this path, of course the project duration will be elongated.
It’s worth to understand that activities on a critical path are critical from schedule point of view only and not from functionality or complexity point of view. Project management practitioners, who are new to this concept, confuse on this. All activities on the critical path are known as critical activities.
Again, the activities are critical, because if you delay any activity on critical path, the project end date will be pushed further.
More the number of critical paths, more the risks to the project. Let’s check this scenario. Imagine you have a schedule network diagram with multiple critical paths. As it has many critical paths, you can say that there are multiple ways in which the schedule can be delayed. Hence, more risks.
Let’s take an example to understand more on it. Below, a simple network diagram is shown with various activities. The duration of the activities is in days, e.g., Activity A is of 5 days duration.
There are 3 different ways to complete the tasks which will take different time to complete as below.
Path -1: Start – A - B – D – F – End = 16 days
Path-2: Start – A – B – E – F – End = 15 days
Path-3: Start – A – C – E – F - End =11 days
But Critical path is Start – A – B – D – F - End being the longest path which takes 16 days to be completed.
Second Definition of Critical Path
There is another definition of critical path as well, which you can see while using project-portfolio management tools such as Microsoft Project or Oracle Primavera. It goes as follows.
“Critical path is the network path in which the total float of activities can be less than or equal to zero.”
Total Float and Free Float
To understand the second definition of critical path, first it requires to understand what total float and free float.
There are two types of floats.
- Total Float (TF): By how much time you can delay the task (or activity) so that it does not delay the project finish date or violate schedule constraint. It can be noted as TF.
- Free Float (FF): By how much time you can delay the task (or activity) so that it does not delay the subsequent task(s) or the successor task(s). It can be noted as FF.
For critical tasks, Total Float can be “0” or can be “Negative”. Critical tasks will have Free Float as “0”. To understand it with an example, you can refer this post:
Primavera P6 - Critical Path is Not Always The Longest Path
Taking one of the figures from the above article, we have two critical paths shown, which are highlighted in read in the graphical side of the Schedule Layout.
Critical Path 1: Start – Activity A – Activity B = 5 days
Critical Path 2: Start – Activity E – Activity – Finish = 8 days
As you can see Activity A is not on the longest path (the path is only of 5 days duration), but still it is highlighted as a critical activity. Because this activity has negative total float of value “-1 day”. Of course, the other two activities – Activity E and F are critical activities, because their TF values are zeroes.
References:
1. “6.6.2.2: Critical Path Method” from PMBOK Guide 5th Edition.
2. “6.7.2 Critical Path Method (CPM)” from Book - I Want To Be A PMP by Satya Narayan Dash.
Brief Profile: Manas Das, Project Manager Infosys Technologies
Manas Das has 12+ years of work experience and is playing a Project Manager role for retail portfolios in NA geography for Enterprise Application Services.
PMP LIVE LESSONS - Guaranteed Pass:
You may also like:
PMP Protein: Conflict, Conflict Management and Conflict Management Techniques
PMP Protein: Top PMP Apps to Assist You
- PMP Protein: Understanding Risk Attitude
- PMP Protein: Information Gathering Techniques
- PMP Protein: How To Be A PMI-PMP
- PMP Protein: How To Prepare and Submit PMP Applications
- PMP Protein: Types of Organizational Structures
- PMP Protein: Identifying Stakeholders
- PMP Protein: Earned Value Management – Basics
- PMP Protein: Strategic Planning, Analysis and Alignment
- PMP Protein: Earned Value Management – Advanced
- PMP Protein: Seven Basic Tools of Quality
- PMP Protein: Gaps in Project Management in India’s Construction Industry
- PMPProtein: Organizational (Project) Management – A Facelift
- PMP Protein: Facing the Sun
- PMP Protein: Project Management Practitioners’ Conference 2018 - A Feast of Knowledge
- PMP Protein: Requirements Gathering Methods
- PMP Protein: Emotional Quotient – A Risk Factor
- PMP Protein: Ensuring Effective Communication by Team Members and Middle Management
- PMP Protein: Leadership and Team Building
- PMP Protein: Understanding Brainstorming
- PMP Protein: Changing Work Cultures and Organizational Impact





No comments:
Post a Comment
Sign- or Log-in and put your name while asking queries in comments. Any comment is welcome - comments, review or criticism. But off-topic, abusive, or defamatory comments will be moderated or may be removed. For queries, please contact managementyogi@gmail.com.