Saturday, December 31, 2022

Management Yogi's Hybrid-Agile (CHAMP) Certification: 20 Free Questions and Answers (Part - 2)



This is in continuation of the earlier series of questions for Management Yogi's Certified Hybrid-Agile Master Professional (CHAMP) certification exam. 

I definitely suggest that you take both the parts together, when you try to attempt the questions. This way you will have continuation in your learning and get a better understanding on what kind of questions may come in your exam. 

Also, as mentioned in the previous series, to answer these questions, you need to have: 
  • Sound understanding of Hybrid-Agile Management.
  • Solid grasp on how Hybrid-Agile management can happen in the real-world. 
  • Good understanding of traditional (waterfall), Scrum and Kanban management.
  • Real world Hybrid-Agile management experience.
  • Critical thinking, logical reasoning, ability to think out of the box.  


Note: The newly enhanced Certified Hybrid-Agile Master Professional (CHAMP) certification has wider coverge, a number of tips and tricks (including a large number of Agile tips), a number of practice questions at the end of lessons. The questions in your CHAMP exam will be mostly situational with hands-on orientation. Hence, you need to prepare from that perspective.  

Again, I hope you enjoy doing these questions and it helps in your preparation for the CHAMP exam.


[This series - Part - 1]


*********

Question – 11: Following Hybrid models have been proposed by the PMO of your organization. They want you to review and confirm one of the models as you are a Certified Hybrid-Agile Master Professional (CHAMP). You disagree with one of the models because it’s not a Hybrid-ScrumBan approach. Which one of the following is that?
A Predictive followed by Kanban, then Scrum and finally predictive.
B Predictive followed by Scrum, then Kanban and finally predictive.
C Adaptive with Scrum, then Kanban and finally predictive.
D Adaptive with Kanban, then Scrum and finally adaptive.

Question – 12: A statue is getting built by a sculptor and his team. The master craftsman is continuously refining it along with the team members and showing it to the customer. Based on the customer’s feedback, again further refinement happens. What kind of life cycle is being used?
A Iterative
B Hybrid
C Iterative and incremental
D Incremental

Question – 13: A pharmaceutical company is developing medical drugs in a project involving high degree of complexity, and risk during the long development part of the project. However, this pharma company has matured and robust development phase, but equally long rollout phase, which is well defined and repeatable. Which kind of approach will BEST help the pharma company in such a case?

A A predominantly predictive approach with some agile components
B A predominantly agile approach with some predictive components
C A hybrid approach combining both predictive and agile
D A iterative and incremental approach 

Question – 14: A Sprint Burnup Chart for a Hybrid-Scrum project is shown below. For this chart ______________ filter and ____________ group are applied.


A Current Sprint, Sprint
B Sprint, Current Sprint
C Current Sprint, Current Sprint
D Sprint, Sprint

Question – 15: A Sprint Planning Board for a Hybrid-Scrum project is shown below. 



You want to show the % Complete value and for each task item (i.e., Card) in this board. What should you do?

A Customize the cards from the Global Settings
B Customize the cards from Sprint Tools > Sprints > Views > Customize Cards
C Add the % Complete field by double clicking on the cards
D Add the % Complete field Task Board Tools > Format > Customize > Customize Cards


Question – 16: For a Hybrid-Kanban project, following the cumulative flow diagram for the Kanban elements in the project.


The board has four workflow states or columns: (Kanban) Backlog, In progress, Next up and Done. What is the work in progress (WIP) for this Kanban board?

A 7
B 8
C Can’t be determined
D 10

Question – 17: For a support project, your team is fixing a number of tickers and you are using a Hybrid approach with some elements in Kanban. In the Task Board Sheet view, you have default values available as shown below. You want to know the actual work for the “In progress” items. What should you do?


A Go to Gantt Chart view to determine the actual work
B Add the “Actual Work” field or column to the Task Board Sheet view
C Add the “Actual Work” field, and then group by Board Status 
D Add the “Actual Work” field, group Board Status and then Work status

Question – 18: In your Hybrid-Kanban project reporting, you want to show all the Done items, as well as the In progress, Next up, and Kanban backlog items. Which view will be MOST suitable?

A Task Board  
B Gantt Chart
C Kanban Board
D Backlog Board

Question – 19: You are Certified Hybrid-Agile Master Professional (CHAMP) and currently managing a Hybrid-Kanban project. To have a clear distinction between the traditional (waterfall) and Kanban part of the project, which field is MOST LIKELY to be used by you as a CHAMP?

A The Boolean custom field of “isAgile”
B The text custom field of “isAgile”
C The Boolean custom field of “isKanban”
D The number custom field of “isKanban”

Question – 20: A Kanban card is shown below for the Task Board view. 


Among fields shown in the card, what are the base fields?

A ID and Resource 
B ID, Resource and 100% Complete checkmark
C Resource, Task Summary Name and Duration 
D Duration, Start and Finish



*********


The question set is available in the embedded document below. The answers are also part of this document.

For all answers, subscribe to this site and send a mail (from your GMail id) to managementyogi@gmail.com.






No comments:

Post a Comment

Sign- or Log-in and put your name while asking queries in comments. Any comment is welcome - comments, review or criticism. But off-topic, abusive, defamatory comments will be moderated or may be removed.